Closures related to the replacement of the safety and weight enforcement facility (SWEF) near Hudson:

Description: Replacing the existing SWEF building with a modern one, reconstructing the parking lots and ramp/loop roadways and constructing an automated truck traffic monitoring system along eastbound I-94, a virtual weigh station along US 12 and an approximate 300-foot communications tower near the new building.

Traffic impacts: Motorists will encounter the following off-site impacts:

Westbound I-94:

  • There will be a continuous median shoulder closure with barrier wall until temporary widening of the eastbound median is removed later this summer.

Eastbound I-94:

  • There will be a continuous left-lane closure in the three-lane portion of I-94 near the US 12 interchange and lane shift until temporary widening of the eastbound median is removed later this summer.

  • There will be a continuous outside shoulder closure with barrier wall at the SWEF ramp locations until tie-in work is completed this summer.

Closures related to the replacement of I-94 bridges over Carr Creek and County NN in St. Croix County and ramp construction:

Description: Building temporary roadway and bridges to maintain four lanes of traffic on I-94; removing and replacing the existing east- and westbound I-94 bridges over Carr Creek and County NN with structures wide enough to allow for an additional lane of traffic on I-94 when warranted; constructing eastbound exit ramp and westbound entrance ramp bridges and realigning the ramps at the I-94-County B interchange; extending the north end of the existing box culvert at County NN; and completing grading operations, approach work, sign installation and pavement marking.

Traffic impacts: Motorists can expect to encounter the following lane closures on I-94 for the coming week (May 1st):

Westbound I-94:

  • 8 p.m. Sunday to 2 p.m. Monday

  • 5 p.m. Monday to 2 p.m. Tuesday

  • 5 p.m. Tuesday to 2 p.m. Wednesday

  • 5 p.m. Wednesday to 2 p.m. Thursday

  • 6 p.m. Thursday to 11 a.m. Friday

  • 7 p.m. Friday to 10 a.m. Saturday

Eastbound I-94

  • 6 p.m. Sunday to 10 a.m. Monday

  • 5 p.m. Monday to 2 p.m. Tuesday

  • 5 p.m. Tuesday to 2 p.m. Wednesday

  • 5 p.m. Wednesday to 10 a.m. Thursday

  • 6 p.m. Thursday to 9 a.m. Friday

  • 8 p.m. Friday to 9 a.m. Saturday

In addition:

  • Traffic at Carr Creek is expected to be switched onto the eastbound crossover Sunday night.

  • County NN will be closed from Wednesday to Friday, May 3 to 5.

  • Motorists will encounter flagging on the eastbound I-94 off-ramp at County B.

Closures regarding Rush River bridges west of Baldwin

 

Description: Building temporary roadway and bridges to maintain four lanes of traffic on I-94; removing and replacing the existing east- and westbound I-94 bridges over the Rush River with structures wide enough to allow for an additional lane of traffic on I-94 when warranted, along with approach pavement; clearing and grubbing ditches; and installing storm sewer, signage, pavement marking, guardrail and fence.

Traffic impacts: Motorists will encounter the following closures for the coming week:

Eastbound I-94 lane closures:

  • 7 p.m. Sunday to 10 a.m. Monday.

  • 5 p.m. Monday to 2 p.m. Tuesday.

  • 5 p.m. Tuesday to 2 p.m. Wednesday.

  • 5 p.m. Wednesday to 11 a.m. Thursday.

  • 6 p.m. Thursday to 9 a.m. Friday.

For more information regarding traffic impacts and transportation news in Wisconsin’s Northwest Region:

Memberships


Add new comment

The content of this field is kept private and will not be shown publicly.


Eye On Dunn County Staff
About

Press releases and other content not written by a specific Eye On Dunn County author are listed as Eye On Dunn County Staff.