Dunn County
Highway: County B
Location: Between US 12/WIS 29 and the eastbound I-94 on- and off-ramps
Schedule: April 1 to November
Cost: $6.98 million
Description: Replacing 1.16 mile of the existing concrete pavement with new concrete pavement; replacing curb and gutter, storm sewer and electrical; and making intersection and traffic signal improvements.
Traffic impacts: From US 12/WIS 29 to I-94, the northbound lanes of County B are closed, and traffic in both directions is operating on the southbound lanes.

  • North of I-94, County B closed from Badger Drive to Packer Drive as part of a Dunn County construction project.
  •  

Highway: County C
Location: Muddy Creek Bridge southwest of Elk Mound
Schedule: May 1 to early August
Cost: $681,160
Description: Replacing the bridge.
Traffic impacts: County C is closed between County J and 790th Street.


Highway: WIS 64
Location: County O north of Boyceville to the north junction of County W
Schedule: May 13 to late August
Cost: $3.35 million
Description: Rehabilitating the bridge over the Hay River by making concrete surface repairs, replacing bridge joints and overlaying the deck with concrete; replacing the culvert carrying Otter Creek; repairing or replacing additional culverts along that stretch; placing new asphalt pavement over culvert replacement sites; and replacing guardrail and pavement markings.
Traffic impacts: WIS 64 is closed to through traffic. Currently, there are hard closures at:

  • The Hay River Bridge between 430th Street and County VV.
  • Otter Creek, the site of a culvert replacement between 1250th Avenue and County SS.
  • Access to local businesses and residences in the work zone is being maintained.
  • Motorists traveling north or south on WIS 25 can use WIS 64 to get to either the northern or southern leg.
  • Nonlocal traffic is being detoured via WIS 79, WIS 170, WIS 40 and US 53.

***

Highway: I-94
Location: Safety and Weight Enforcement Facility (SWEF) on westbound I-94 east of Menomonie
Schedule: March 19 to November
Cost: $10.95 million
Description: Renovating and expanding the existing SWEF building; replacing the pavement in the parking lots and on the ramp/loop roadways; constructing an approximate 200-foot communications tower near the renovated SWEF building; reconfiguring the exit off I-94; constructing a new virtual weigh station along westbound US 12/WIS 29 west of the I-94 interchange; and constructing a remote truck pull-off site along County B south of I-94 between Walton Avenue and 3M Drive in Dunn County. (The pull-off site will be constructed concurrently with a reconstruction project scheduled to start April 1 on County B from US 12/WIS 29 to the eastbound I-94 entrance and exit ramps at the I-94/County B interchange.)
Traffic impacts: The ramp off westbound I-94 to the SWEF is closed. Other impacts include:

  • I-94 westbound:
    • Motorists might encounter outside lane closures during off-peak travel times.
    • The right, or driving, lane, will be closed from 6 p.m. Monday, June 24 to 2 p.m. Wednesday, June 26.
  • I-94 eastbound:
    • Off-peak closures are expected to start the week of July 8.
  • US 12/WIS 29 west of the I-94 interchange:
    • Shoulders will be closed as needed.

***

Eau Claire County
Highway: Fairfax Street
Location: South Hastings Way in Eau Claire to Spooner Avenue in Altoona
Schedule: March 27 to August
Cost: $3.18 million
Description: Replacing the pavement, curb, gutter, sidewalk, sewer and water utilities; and driveway approaches to the road.
Traffic impacts: Fairfax Street is closed to through traffic but has limited access, and motorists are asked to use South Hastings Way or surrounding local streets.

  • There is no access to Spooner Avenue through Fairfax or surrounding streets; motorists must take South Hastings Way.

***

Highway: County F (State Street)
Location: Heather Road to Hamilton Avenue in Eau Claire
Schedule: May 13 to late October
Cost: $3.3 million
Description: Placing new asphalt pavement; replacing sanitary and storm sewer and water main; replacing existing concrete curb and gutter and adding curb and gutter where it currently doesn’t exist; and placing new pavement markings.
Traffic impacts: County F (State Street) is closed to through traffic from East Lowes Creek Road to Hamilton Avenue.

  • Through traffic is being detoured via East Lowes Creek Road, Golf Road, Rudolph Road and Hamilton Avenue.
  • Those who live in the work zone can access State Street via Hamilton Avenue or East Lowes Creek Road.
    • Due to contractor staging, the pavement on State Street from about Tamarack Lane to Hamilton Avenue currently remains to allow residents to use that area.

***

Highway: I-94
Location: US 53 interchange to Mallard Road southwest of Eau Claire
Schedule: March 4, 2024, to November 2026
Cost: $69.9 million
Description: Removing and replacing the pavement on I-94 from Otter Creek to Mallard Road; resurfacing the shoulders and completing concrete pavement repair on I-94 and collector roads from the western project limits to Otter Creek; resurfacing the I-94/US 53 interchange, the approaching pavement on US 53 and the interchange ramps; widening the eastbound I-94 bridge over Otter Creek; removing and replacing the east- and westbound bridges over County D and County J with structures that meet vertical clearance requirements and are wide enough to handle future four-lane temporary traffic; removing and replacing a box culvert near County D; repairing storm sewer; and placing new pavement markings.
Traffic impacts: Motorists will encounter single-lane closures in both directions and a reduced speed limit of 55 mph during nonpeak travel times.

  • County D is closed at I-94.


 

Memberships


Add new comment

The content of this field is kept private and will not be shown publicly.


Eye On Dunn County Staff
About

Press releases and other content not written by a specific Eye On Dunn County author are listed as Eye On Dunn County Staff.